This quiz is a review of the Completed Update Form information presented in this Lesson. You must receive an 80% score on this quiz to proceed to the next lesson in the Duration-Driven course.
If you find yourself stumped, you may navigate back to the lesson menu and review any of the topics or videos in this section and then navigate back to the quiz to retake it. You can retake the quiz as many times as necessary to receive a passing score. Good luck!
0 of 6 Questions completed
Questions:
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading...
You must sign in or sign up to start the quiz.
You must first complete the following:
0 of 6 Questions answered correctly
Your time:
Time has elapsed
You have reached 0 of 0 point(s), (0)
Earned Point(s): 0 of 0, (0)
0 Essay(s) Pending (Possible Point(s): 0)
The update information has been entered into the remaining network diagram activities below up to the Install Yard Signs activity.
Forward Pass
Early Start (ES) = Latest Early Finish (EF) for All Preceding Activities
Early Finish (EF) = Early Start (ES) + Duration (D)
What is the Early Start and Early Finish for Installing the Yard Signs?
Forward Pass
Early Start (ES) = Latest Early Finish (EF) for All Preceding Activities
Early Finish (EF) = Early Start (ES) + Duration (D)
What is the Early Start and Early Finish for the Organize/Hold Pancake Breakfast Event?
The rest of the Forward Pass calculations are shown below.
What is the overall duration of the project now?
The election is scheduled in 100 days but the current plan shows we will complete in 105 days. What does that imply?
Look carefully at the connection arrows in the network diagram.
What do the red arrows signify?
Remember the update report. We have $11,000 in the campaign account. We could select multiple options to compress this project and get it back on track. Study the remaining activities in the network diagram and the remaining compression/crashing options listed below.
What is the best compression or crashing option based on the data we have?