This quiz is a review of the information presented in this Lesson. It is a review of everything you learned so far. You must receive an 80% score on this quiz to proceed to the next lesson in the Duration-Driven course.
If you find yourself stumped, you may navigate back to the lesson menu and review any of the topics or videos in this section and then navigate back to the quiz to retake it. You can retake the quiz as many times as necessary to receive a passing score. Good luck!
0 of 11 Questions completed
Questions:
You have already completed the quiz before. Hence you can not start it again.
You must sign in or sign up to start the quiz.
You must first complete the following:
Quiz complete. Results are being recorded.
0 of 11 Questions answered correctly
Your time:
Time has elapsed
You have reached 0 of 0 point(s), (0 )
Earned Point(s): 0 of 0 , (0 )
0 Essay(s) Pending (Possible Point(s): 0 )
If you received a score of 80% or higher, you may proceed to the next lesson. If not, please restart the quiz to proceed.
Great work! You can now proceed onto the next lesson topic!
Current
Review
Answered
Correct
Incorrect
Question 1 of 11
Should project managers be Subject Matter Experts (SMEs) in the technical areas of their project?
Select Each Answer That Applies.
Question 2 of 11
Assign the correct Role to each Effective Characteristic by dragging and dropping the Role to the Right of the Characteristic.
Project Manager
Team Member
Project Sponsor
Lead the team to produce the end deliverables within the constraints of time, cost, resources, and technology.
Correct
Incorrect
Correct answer
Highly committed to the purpose, goals and approach of the team, customers, and stakeholders.
Correct
Incorrect
Correct answer
Are willing to set priorities for the team and understand that there may be a time/cost/quality implication for lower priority projects.
Correct
Incorrect
Correct answer
Question 3 of 11
Assign the correct Role to each Effective Characteristic by dragging and dropping the Role to the Right of the Characteristic.
Project Sponsor
Team Member
Project Manager
Are able to assist the team in dealing with the organizational context of the project.
Correct
Incorrect
Correct answer
Able to translate broad objectives into specific and measurable deliverables and action plans.
Correct
Incorrect
Correct answer
Identify the skills needed on the team, and negotiate with the resource managers for assignment of appropriate people.
Correct
Incorrect
Correct answer
Question 4 of 11
Assign the correct Role to each Effective Characteristic by dragging and dropping the Role to the Right of the Characteristic.
Team Member
Project Sponsor
Project Manager
Willing to frequently and honestly assess their progress against goals.
Correct
Incorrect
Correct answer
Are willing to personally participate in planning and control activities in order to demonstrate the organization’s commitment to project management.
Correct
Incorrect
Correct answer
Track project elements such as milestones, deadlines, schedules, resource utilization, budgets, risks, changes of scope, and quality of deliverables.
Correct
Incorrect
Correct answer
Question 5 of 11
What differentiates Managed Scope Change vs. Scope Creep?
Select Each One That Applies.
Question 6 of 11
Match each of the Project Charter elements to the Key Question it answers by dragging and dropping the Project Charter element to the Right of the Key Question.
Background
Project Objectives
Time/Cost Tradeoff
Project Scope
Stakeholders
Constraints
Assumptions
Risks
What is the project History?
How significant is the Gap or Problem we are trying to address?
Correct
Incorrect
Correct answer
Why are we doing the project?
Correct
Incorrect
Correct answer
How Much is it costing the company to not have the project complete?
Correct
Incorrect
Correct answer
What are the deliverables the project will produce and what is specifically excluded from delivery?
Correct
Incorrect
Correct answer
Who is needed to complete the project or who will be impacted by the project?
Correct
Incorrect
Correct answer
What Limitations exist that we have to work within?
Correct
Incorrect
Correct answer
What Key Decisions have been made by the team about the project?
Correct
Incorrect
Correct answer
What could go wrong?
Correct
Incorrect
Correct answer
Question 7 of 11
What is the Purpose of the Background element in the Project Charter.
Question 8 of 11
What is the Purpose of the Project Objectives element in the Project Charter?
Question 9 of 11
What is the Purpose of the Time/Cost Tradeoff element in the Project Charter?
Question 10 of 11
What is the Purpose of the Project Scope element in the Project Charter?
Question 11 of 11
Match the remaining Charter Elements to the Purpose they support by dragging and dropping the Charter Element to the Right of the Purpose.
Title of the Project
Date/Revision Number
Stakeholders
Constraints
Assumptions
Risks
Signature Line
Differentiate the project from all others that may be active in the organization.
Correct
Incorrect
Correct answer
Determine whether this document is the most current version.
Correct
Incorrect
Correct answer
Ensure the right people are on the team to complete the deliverables and approve the charter.
Correct
Incorrect
Correct answer
Delineate time, budget, resource, and technology restrictions.
Correct
Incorrect
Correct answer
Allow the creation of a schedule even if all decisions impacting the project have not been provided.
Correct
Incorrect
Correct answer
Ensure the approach and schedule address potential pitfalls.
Correct
Incorrect
Correct answer
Confirm all Stakeholders have read & will support the project as chartered.
Correct
Incorrect
Correct answer