This quiz is a review of the Estimating Activity Duration information presented in this Lesson. You must receive an 80% score on this quiz to proceed to the next topics in the Duration-Driven course.
If you find yourself stumped, you may navigate back to the lesson menu and review any of the topics or videos in this section and then navigate back to the quiz to retake it. You can retake the quiz as many times as necessary to receive a passing score. Good luck!
0 of 16 Questions completed
Questions:
You have already completed the quiz before. Hence you can not start it again.
You must sign in or sign up to start the quiz.
You must first complete the following:
Quiz complete. Results are being recorded.
0 of 16 Questions answered correctly
Your time:
Time has elapsed
You have reached 0 of 0 point(s), (0 )
Earned Point(s): 0 of 0 , (0 )
0 Essay(s) Pending (Possible Point(s): 0 )
Show Question
1
Show Question
2
Show Question
3
Show Question
4
Show Question
5
Show Question
6
Show Question
7
Show Question
8
Show Question
9
Show Question
10
Show Question
11
Show Question
12
Show Question
13
Show Question
14
Show Question
15
Show Question
16
Review
Answered
Correct
Incorrect
Question 1 of 16
Effort does not equal Duration. Why could an activity that requires “3 Days of Work” have a duration of several weeks?
Question 2 of 16
If the update cycle is every week, what would be an appropriate duration for near-term activities?
Question 3 of 16
Imagine an Activity Owner said, “We have completed activities like this five times over the past year. Based on our recorded actual durations, we expect this will take a week and a half.” What estimating technique did they use?
Question 4 of 16
Imagine an Activity Owner said, “I have consulted the industry standards for installing carpet. Based on the square footage we need to cover, we expect this activity to require two weeks.” What estimating technique did they use?
Question 5 of 16
The “Normal Point” is the most efficient means of completing the activity. What is likely to happen to the duration after doubling the resources assigned to complete the activity?
Question 6 of 16
What could happen to the duration and the cost of an activity when there are too many resources assigned?
Question 7 of 16
Consider a low priority activity that will likely be interrupted several times before it can be completed. What is the likely duration for this activity?
Question 8 of 16
Considering the Activity Time-Cost Tradeoff graph, what is the Normal Cost for an activity?
Question 9 of 16
Considering the Activity Time-Cost Tradeoff graph, what is the Normal Duration for an activity?
Question 10 of 16
Considering the Activity Time-Cost Trade-Off graph, what is the Crash Duration for an activity?
Question 11 of 16
Considering the Activity Time-Cost Tradeoff graph, what is the Crash Cost for an activity?
Question 12 of 16
What is the most likely reason for management to require everyone to work overtime on a project that is running behind schedule?
Question 13 of 16
Imagine there is an experienced resource that can be assigned to a project activity. We estimate that it will take 5 hours for them to complete the activity and that they can make themselves available to work on it for 1 hour per day. Using the formula, Duration = Resource Requirements ÷ Resource Availability, what would be the duration of the activity?
Question 14 of 16
Imagine there is an inexperienced resource that can be assigned to a project activity. We estimate that it will take 10 hours for them to complete the activity and that they can make themselves available to work on it for 5 hours per day. Using the formula, Duration = Resource Requirements ÷ Resource Availability, what would be the duration of the activity?
Question 15 of 16
Given the last two questions, who should be assigned to work the activity, the experienced or inexperienced staff member?
Question 16 of 16
Given everything we have discussed about estimating duration, which of these happens most frequently?